Real Building Advisors · Mon–Fri 8AM–5PM MT587-800-4629Text us

Order this winter, standing by spring. Production orders run about 60 days.How spring orders work

How Our Buildings Are Anchored

Understand the available anchoring approaches and what information is needed to select one for your building and site. Confirm the applicable design and installation instructions before preparing the base.

The short version

A concrete foundation is not required for every project. Supplied ground stakes are one approach; concrete, piles or other systems may be needed for the building and site. Confirm soil conditions, foundation and connection requirements, intended use and applicable design documents before choosing. A permit exemption does not establish anchor capacity.

Planning guide: the illustrations explain possible arrangements. Use the current design and installation documents issued for your project.

1. Compare the approaches

Use this table to discuss possible approaches. It does not select or size a foundation. Conditions, equipment access and the applicable design determine what can be installed and when.

Site conditionApproach to discussHardwareInstallation conditions
Packed earth — most farm and acreage sitesGalvanized stakesIn the boxUntil the ground freezes
Concrete you have or will pour — slab, footings, piersWedge anchorsYou or your installerConfirm design and product limits
Livestock or machinery inside, or want more heightPrecast blocks + wedge anchorsYou arrange blocksConfirm design and product limits
Restricted ground penetration or difficult soilsBallast blocksYou arrange blocksConfirm design and product limits
Loose gravel, sand, soft groundScrew pilesPile contractorConfirm ground and installation limits
Bare rockEpoxy rock anchors, or a small pad on the rockYou or your installerConfirm design and product limits

In the box

Footplates and the full set of galvanized stakes — four per footplate. The count is on your packing list.

Not in the box

Wedge anchors, blocks, screw piles, epoxy, cables, concrete. When MAX installs, anchoring hardware beyond the stakes is listed on your estimate.

2. What anchoring does

Wind is the load anchoring answers. It does three things to a building at once: it pushes on the side, it lifts the roof, and it tries to tip the whole frame. The anchoring system must transfer those actions through the footplates and connections into the foundation or ground.

How much holding you need depends on your building, your site’s wind and snow, and what it stands on. We do not print a holding number here: a number that is not for your site is not one you can use. An appropriately licensed engineering provider can assess the anchoring for the agreed project scope. Follow the instructions applicable to the exact building and site; an exemption from a permit does not prove that supplied stakes suit the ground.

Stakes, frost and the manual. The supplied stakes are not intended for rocky ground, frozen ground or concrete. Ground movement can affect foundations and anchors. Follow the project inspection and maintenance instructions and have movement or loosened connections assessed before treating the anchoring as sound.

Before the roof goes on

Use the erection sequence, temporary bracing and anchoring instructions issued for the exact building. Resolve missing or conflicting instructions before raising the frame; a general website illustration cannot replace the erection plan.

1 · pushes the side 2 · lifts the roof 3 · tips it the footplates and anchors hold all three

Wind pushes, lifts and tips. The anchoring resists all three through the footplates.

1

Galvanized Steel Stakes

The standard · in the box
Consider forSoil conditions for which the supplied stake system and applicable project documents establish suitability. Do not infer holding capacity from driving resistance alone.
SeasonConfirm ground conditions at the time of installation. Do not drive the supplied stakes into frozen ground.
In the boxYes. Four stakes per footplate, hot-dip galvanized. 30′ series: 14 mm × 700 mm. 40′ and wider: 16 mm × 1000 mm. The full count ships with the building.
You arrangeInstallation equipment, utility-location information and site preparation appropriate to the applicable instructions.
On build dayFollow the applicable layout, stake-installation and erection instructions for the exact kit. Required anchoring and temporary bracing must be in place at the stages specified in those instructions.
Watch forSoft, wet or recently filled ground requires assessment; changing to blocks, piles or ballast also needs a suitable design. Follow the project maintenance and inspection requirements.
Stakes in the box, by sizeFrom the factory packing lists. Four per truss footplate; end-wall and door plates take two or four. 20×40: 56 · 30×40: 48 · 30×50: 64 · 30×60: 80 · 40×60: 72 · 40×80: 88 · 40×100: 104 · 50×100: 108 · 50×150: 158 · 50×200: 196 · 60×120: 180 · 60×150: 220 · 70×150: 220 · 70×200: 284. Other sizes: ask us, or read your packing list.
Four galvanized stakes driven through each footplate Cross-section cartoon of a truss footplate on the ground with four one-metre galvanized stakes driven through it into the soil. ground truss leg footplate driven to full depth 4 per footplate · 8 per truss

Four galvanized stakes through every footplate, driven on the angle to full depth.

2

Wedge Anchors into Concrete

Slab, footings or sonotube piers · project-specific
Consider forA slab, footing or pier designed or assessed for the building and its anchor forces. An existing slab is not automatically a suitable foundation; thickness, reinforcement, condition, edges and connection details matter.
SeasonConcrete condition, curing and anchor-product installation limits must be satisfied.
In the boxNo.
You arrangeWedge anchors sized to your drawings or your engineer; a hammer drill, masonry bit and wrench.
On build dayInstall the specified anchors to the project details and the anchor manufacturer's instructions, including hole preparation, embedment, spacing, edge distance and installation torque.
Watch forAnchors need solid concrete with room to the edge — a thin or cracked slab edge will not hold. Concrete is permanent: settle where the doors go before you pour.
3

Precast Blocks + Wedge Anchors

Livestock & machinery · adds height · project-specific
Consider forProjects with a designed precast-block arrangement. Raising the building changes its geometry and connections and must be included in the project assessment.
SeasonConfirm site conditions and product installation limits.
In the boxNo.
You arrangeBlocks and placement equipment matching the agreed design, with specified connections. Do not select a block arrangement using a generic block weight.
On build dayBlocks set level, in a straight line to the layout drawing. The building bolts to the top of the course.
Watch forRaising the building affects doors, connections and the enclosure. Include those changes in the design and installation scope. Obtain prices for the complete block, transport and placement arrangement.
Building set on stacked concrete blocks with wedge anchors, forming a wear wall Cartoon cross-section of a fabric building baseplate wedge-anchored to interlocking concrete blocks, with a cow rubbing against the block wall instead of the cover. design-specified blocks configuration by design baseplate wedge anchors the wear wall: rubbing hits concrete, never the cover

Illustration of a block-supported arrangement. Block configuration, connections and any barrier function must match the project design.

4

Ballast Blocks

Designed ballast · no ground penetration
Consider forA designed ballast arrangement where ground penetration is restricted or another foundation is unsuitable. Ground bearing, sliding, overturning and connections require assessment.
SeasonConfirm ground bearing, access and placement conditions. No ground penetration is shown in this example.
In the boxNo.
You arrangeBlocks and a loader. Your engineer specifies the block weight and the tie-down from block to frame.
Watch forA block’s lifting ring is for lifting the block. The permanent tie-down is a rated anchor point the engineer specifies.
5

Screw Piles

Gravel, sand & soft ground
Consider forProjects where the ground investigation and pile design support this approach. Loose surface material alone does not establish the required pile capacity or depth.
SeasonConfirm ground access, installation limits and specialist availability.
In the boxNo.
You arrangeA pile contractor. Your engineer sets the pile size and depth.
On build dayInstall piles and connections to the project design and specialist installation requirements. The drawing below illustrates a possible arrangement; it does not establish pile count, depth or capacity.
Watch forThe pile arrangement and any tie-down attachment must be designed for the actual structure. Do not alter the frame or substitute a cable connection without the appropriate design.
gravel / sand / soft ground firm ground below truss leg footplate bolted to the pile cap helix grips the firm layer

Illustration of a pile-supported footplate. The project design determines the arrangement, capacity and installation requirements.

6

Bare Rock

Epoxy anchors or a small pad · project-specific
Consider forExposed bedrock.
SeasonConfirm site conditions and product installation limits.
In the boxNo.
You arrangeA rotary hammer and either epoxy anchor rods or a small concrete pour. Your engineer specifies which.
Two waysThe illustrations show A: a connection into rock and B: a concrete foundation connected to rock. A qualified designer must determine which arrangement, if either, suits the rock, building and site. Use the specified materials and installation details.
Watch forDo not treat an anchor intended for concrete as a specified rock anchor. Confirm the rock condition, bearing surface and connection details with the responsible designer.
bedrock A · sound, flat rock grout bed threaded rods set in epoxy B · broken or sloped rock pad wedge anchors into the pad,pad doweled into the rock

Rock, two ways. A: epoxy rods into sound rock. B: a small pad on broken or sloped rock, wedge-anchored like concrete.

Before build day

  1. Grade it rough and keep it dry. Ground slopes away from the building, or a gravel pad a few inches thick where the site holds water. A gravel pad also drains and is the easiest surface to re-level after frost.
  2. Confirm your method with us before the building ships. Blocks, piles, concrete or rock work is done before the crew or the box arrives.
  3. Call before you dig. Stakes go up to a metre down; piles go deeper.
  4. Lay out the footplates to the layout drawing in your package and square it on the diagonals before anything is fixed.
  5. Anchor every plate before the roof section goes up. Read the one-page erection warning.

Moving the building later? Stakes pull out and piles unscrew. Concrete stays where you poured it.

Permits and stamping

Requirements vary by project and jurisdiction. MAX coordinates the building and site information with our engineering partner. The firm confirms acceptance, assesses the agreed scope and issues the professional documents it is responsible for. Foundation and anchoring design, site visits and authority responses must be identified in the quotation. The permit authority decides approval.

Anchoring questions

Do I need a concrete foundation for a fabric building?

Not for every project. The foundation and anchoring must suit the exact building, soil and intended use. Supplied stakes are one approach; a concrete foundation or another designed system may be required. Confirm the applicable documents before choosing.

Are the anchors included?

The stakes are: four per footplate, the full count on the packing list. Wedge anchors, blocks, screw piles, epoxy and concrete are not in the box. When MAX installs, anchoring hardware beyond the stakes is listed on your estimate.

How many stakes does my building take, and how big are they?

Four per truss footplate; end-wall and door plates take two or four. The factory packing lists give 56 on a 20×40, 48/64/80 on a 30×40/50/60, 72 on a 40×60, 88 on a 40×80, 104 on a 40×100, 108 on a 50×100, 158 on a 50×150, 196 on a 50×200, 180 on a 60×120, 220 on a 60×150 and 70×150, and 284 on a 70×200. The 30′ series ships 14 mm × 700 mm stakes; 40′ and wider ship 16 mm × 1000 mm. Your packing list states the total.

Can I anchor after the ground freezes?

The supplied ground stakes are not for frozen ground. Other systems may be possible, but the design, ground conditions and product installation limits must support the proposed winter work. Confirm the installation plan before booking.

What about bedrock?

Rock anchors or a concrete foundation connected to rock may be considered after assessment. The rock condition, connection design and installation requirements must be established for the project. The illustrations on this page are not installation specifications.

How strong is the anchoring?

Capacity depends on the exact building, connections, foundation or ground, and design requirements. Follow the applicable project documents. A stake count, illustration or permit exemption does not establish holding capacity for your site.

Can I move the building later?

Relocation requires planning for dismantling, component condition, the new site, anchoring and any approvals. Confirm whether the existing design and components can be reused before moving the building.

Tell us about your site

Send the building size, address, ground information and any existing foundation documents. MAX can coordinate an engineering request to establish the professional scope required.

Start my engineering enquiry Text 587-800-4629
Call Now Text Us